-
Plan and install natural practices to filter and infiltrate stormwater in the Channel before it reaches Trail Creek
-
Create or enhance 5 acres of wetlands to improve riparian ecosystem
-
Reduce likelihood of Cheney Run Channel scouring Trail Creek banks
-
Install recreation amenities like fishing access sites, trails, and more
Project Summary
Karwick Park/Cheney Run Walkthrough April 6, 2019
The "Before" Pictures






Project Team
Sanitary District of Michigan City
Michael Kuss, General Manager
Steven Stanford, Operations Manager
Alliance for the Great Lakes
Ethan Brown, Senior Community Planning Manager
Delta Institute
Ben Shorofsky, Specialist
Jack Eskin, Senior Specialist
V3 Companies & Ciorba Group
Ted Blahnik (V3)
Tom Slowinski (V3)
Tony Wolff (Ciorba)




Timeline of WHY this Project is Happening
-
Past: Former natural Cheney Run stream was turned into a piped stormsewer system and channel
-
1965-1971: Karwick Nature Park used as an unofficial dump site
-
1972: Dump was closed and covered with sand. Plants naturally took over the site.
-
2013: A strong rain storm event overloaded the Cheney Run Channel and Trail Creek. Old trash underneath exposed. Emergency repairs were undertaken.
-
2014-2016: A Feasibility Study was prepared on various potential projects to manage and treat the stormwater flow in the Cheney Run Channel.
-
Cheney Run Stormwater Wetland Updated Schedule
with Target Completion Dates
January 2019
Kick-off Meeting with Project Team and Engineering Team 1/11/2019
February
Tree Survey (subject to weather conditions) 2/8/2019
Review H&H Models, Groundwater Baseline 2/8/2019
Coordinate with regulators (IDEM) 2/8/2019
Workshop 1: Visioning - TCWP Meeting 2/13/2019
Workshop 2: Visioning – @ DNR Offices & Krueger Memorial Hall 2/26/2019
March
V3 Deliverable: 30% Preliminary Engineering Plans 3/6/2019
Project Team reviews and comments on 30% Plans 3/13/2019
Workshop 3: Feedback - TCWP Meeting 3/13/2019
Workshop 4: Feedback – Big Meeting @ Krueger Memorial Hall 3/21/2019
April
V3 Deliverable: 70% Preliminary Engineering Plans 4/12/2019
Project Team Reviews and Comments: 70% plans, draft permit applications, model updates 4/12/2019
V3 Deliverable: Submit 70% Plans and Permit Applications to USACE, IDEM, IDNR 4/26/2019
May - June
Agency Review (Est 60 days) & provide comments 6/25/2019
July
V3 Deliverable: Revise and resubmit to agencies per comments 7/25/2019
August - September
Agency Final Review & Approval (Est 60 days) 9/23/2019
October
V3 Deliverable: Completed 100% Engineering Plans/bid docs 10/23/2019
RFB Released 10/23/2019
November
Construction Contractor Selected 11/25/2019
December 2019 -March 2020
Construction Period 3/31/2020